Local Donations December 2020

On Wednesday, 16/12/20, Gweedore Windfarm made the following donations: Dunlewey Development €1000 Ionad Naomh Phadraig €1000 Ionad na Sean Daoine €1500 Donegal Cancer Flights €1500 Comharchumann Fobartha Ghaoth Dobhair €1000 Local St Vincent De Paul €500 Gweedore GAA €500 Gweedore Read more…

Local School Donations

Local Donations 2020

Eoghan and Owenie Gillespie, on behalf of Cronalaght wind farm, recently (14/8/20) presenting all of the nine local schools with donations of €1,500 to help with their preparations on reopening during the covid epidemic. The schools are: Scoil Bhríde Meeachladaigh, Read more…

Gweedore Windfarm - Denmark Ambassador Visit

Update December 2019

Since our last update in July 2019, the erection of the 5 turbines went smoothly and the windfarm was ready for energisation at the beginning of August. However, the delay in energisation of ESB 110kv substation at Ardnagappary continued until Read more…

Update July 2019

Since our last update, a lot of work has been carried out on the Gweedore wind farm project. In the first quarter of the year all five turbine foundations were poured. Three of these foundations had to be piled. Non-piled Read more…

Commencement of Ducting

Work has started on the undergrounding of the ducting, which will containing the cables for connecting Gweedore Windfarm to the ESB electricity network. The landowners along the public road are aware of this work and Gweedore windfarm has consulted with Read more…

Site Layout

The 5 new turbines will be located in a semi circle below the existing windfarm; The set back distance between the nearest turbine and the nearest dwelling is 1.2km and the windfarm will operate well within permitted noise levels. The Read more…