Update July 2019

Since our last update, a lot of work has been carried out on the Gweedore wind farm project. In the first quarter of the year all five turbine foundations were poured. Three of these foundations had to be piled. Non-piled foundations took 372m2 of concrete for the base and 44.5 Read more…