Update December 2019
Since our last update in July 2019, the erection of the 5 turbines went smoothly and the windfarm was ready for energisation at the beginning of August. However, the delay in energisation of ESB 110kv substation at Ardnagappary continued until late August, almost 4 weeks delayed. As soon as Ardnagappary Read more…